Sunday, April 18, 2010
Main Room Just About Finished
Dave Frederick and I finished the down stairs. He was a major help in getting it all done. Thanks Dave! We got held up a little waiting for the woodstove guys to punch the whole in the roof for the chimney but all in all it went pretty smooth.
Monday, March 15, 2010
Enjoying Juneau
After lots of work on the house, while Kristen was home we took the boat out a few times and got to enjoy some beautiful views with Chachi too.
First Tiling Job
Kristen, Norm, and I put this slate floor in the utility room. It came out pretty good and I think looks neat with the different colors of slate in it.
Kenny
Cousin Kenny came and got us all sorted out on putting up sheetrock. He helped us with the most challenging parts like doing the areas above the stairs and some of the high cielings. It was good to have him around.
Sunday, March 14, 2010
Back at it!
Kristen got back the beginning of February after working in Oregon. It was great to have her back and she did tons of work on the house while she was home! We sheetrocked the kitchen, planned out the tile for the bathroom, tiled the utility room, got her cousin Kenny up to Juneau and we all sheetrocked the second floor, and was just really nice to spend time with!
Linemen
AELP linemen strung the cable across for the permnant electic power. We were responcible for the service box outside and the mast and they are responsible for everything else i.e overhead lines, transformer, pole .... It felt really good to have this part done. Not so many extension cords!!
Permnant Electric
AELP our local electric company came and had to change out the transformer. The current transformer wasn't big enough to handle the 400 amp service we required for the house due to the electirc boiler we installed.
Vapor Barrier
Put up 6 mil plastic vapor barrier on all the exterior walls and cieling. Lots of stapling but it makes the rooms actually start to look like something.